Increase number of Running Concurrent Requests in R12

Increase number of Running Concurrent Requests in R12


Step-1 Log in to system, switch responsibility to System Administrator.
Step-2 Go to Concurrent > Manager > Define
Step-3 Query 'Standard Manager' there, press Work Shifts button.
Step- 4 Increase the Processes column to required number. (In following case 5 Concurrent Requests can run at once.).